§ 12.12.105. Public relations and community outreach.  


Latest version.
  • Utility company must maintain a policy for community notification and outreach for planning and design of utilities that may take longer than 30 days to complete, or may in the opinion of the Director of Public Works have significant impact on traffic, parking, access to homes and businesses, Director of Public Works may require that the utility company must submit a set of construction plans with a complete public outreach plan and conduct community outreach and public relation efforts addressing detours, traffic control, duration, and address the community's concerns. Utility company shall be prepared to show purpose and the nature of the project, alternatives, proposed route, scope, duration, short and long term impacts, traffic impact, project benefits, and accommodations for the community to maintain their daily lives.

(Ord. No. 13300, § 1, 3-31-2015)